im using a student version of NavisWork manage 2011 doing my final year project.
when i add .mpp, MSproject2003 into TimeLiner--Likns, only one line come out, saying'New link' something, and how exactly should i make a time line? in Tasks?
can i just link .mpp file into it or ishould create a task schedule under Task?
i have read about User Guide and Getting started guide, seems not cover that area.
thank you very much!!!