Hello everybody,
I want to use a MS-project schedule in my Navisworks project. This is my first time I'm going to use this feature, so maybe i'm missing some knowledge. I first had Navisworks Manage 2016 installed on my pc (I think about a year now) and since yesterday MS Project 2010 (I learned the hard way I need it on my pc if I want to make the connection ;-))
Now, I open my Navisworks-project and also my MS-project with schedule. Then I go in Navisworks to the TimeLiner and the Tab Datasources. I choose Add Microsoft Project 2007-2013. When I do that Navisworks crashes instantly (see attachment for screenshot)
Am I doing something wrong?
I've already tried a different Navisworks-project and a simple new schedule (only 3 tasks). But everytime the result is the same, instant crash.
I hope someone is able to help me.
With kind regards,
Lineke