Completed task in timeliner

Completed task in timeliner

Anonymous
Not applicable
699 Views
3 Replies
Message 1 of 4

Completed task in timeliner

Anonymous
Not applicable

Hi, 
is there a solution to keep the text of the completed tasks in the timeliner simulation ?

0 Likes
700 Views
3 Replies
Replies (3)
Message 2 of 4

Anonymous
Not applicable

Try out iFBIM from iFieldSmart,

 

http://ifieldsmart.com/index.php

 

You can upload your data including clashes, viewpoints, timeliner, your documents, etc. to a cloud shared environment so that your team can access it from their anywhere.

You can use the CVP Sync Plugin from iFieldsmart to sync your data between Navisworks and the iFBIM web portal. You can download it from the Autodesk app store.

0 Likes
Message 3 of 4

Anonymous
Not applicable

is it the way for my question ? 
i'd delete the text from the timeliner simulation in Navisworks. 

0 Likes
Message 4 of 4

mohamedelimam
Enthusiast
Enthusiast

Screenshot (123).pngFrom Timeliner panel, Simulate, Settings, then Edit "Overlay text". 