Sorry for confusions... Let me clear it.
Don't know if I am going wrong but I worked out my job making assemblies as below.
.
1. SubAssembly "MAIN BASE FRAME.iam" - inludes complex frame structure which doesn't change any parts but changing only sizes of used parts like "Channels and Brackets" for 50 different options.
2. SubAssembly " BASE SUB.iam" - includes Base Plates which chages Sizes, holes etc.
3. SubAssembly " PIPEWORK.iam" which includes PUMPs and PIPEWORKs. That need to change 50 different PUMPS and so 50 different options for PIPEs & Valves to different options (Like PE, SS, DICL Pipes also differnt sizes and Number of different valves etc).
4. Top Assembly "FINAL.iam" - includes all three SubAssemblies.
I Said 50 Options but I got hundreds of Options in real with a huge list of different Pump models.
Now I need to make 10 drawings as below.
"FINAL.iam" with all Subassemblies. FOR CONSTRUCTION
"FINAL.iam" with all Subassemblies. FOR CLIENT
"FINAL.iam" with removing "MAIN BASE FRAME.iam" Subassembly. FOR CONSTRUCTION
"FINAL.iam" with removing "MAIN BASE FRAME.iam" Subassembly. FOR CLIENT
Two drawings (includes diffent Views, Sections & Part list) for each of Three Subassemblies FOR CONSTRUCTION.
The Main Problem I am getting is as example below.
I made all the changes as per Option-1 and Printed all drawings Yesterday.
Again, I am making all the changes as per Option-2 to get all drawings Today.
Again, I will get few changes in Option-1 Tomorrow. So have to do it again what I did Yesterday.
I don't know if I can do it any different better way.
Sorry for a long story.
Many thanks.