Why not?
Because it's an extra step I shouldn't have to do.
Thus the "option" comment.
Re: the original phasing, We often use the Bind Link process when we do a subsequent remodel in a project.
We do a lot of Health Care projects and, since we've been using Revit for over 10 years, we've got a many projects that we already have a Revit model for. The "master" model then is all converted to "existing". Many of our projects have multiple Bid Pack phases, and we don't want to drag those long into a new project. We'd end up with dozens or even hundreds of obsolete, unnecessary "phases"