Anuncios
Welcome to the Revit Ideas Board! Before posting, please read the helpful tips here. Thank you for your Ideas!

Add Phasing to grids and levels

Make it possible to add Phasing to Grids and Levels. So when demolishing a Floor or an entire wing of a building we can also "demolish" the corresponding Grids and Levels.

Comentarios
Contributor
Contributor

We got an idea to link levels to phases.

When you do have an existing building, you can link the levels from the existing building to the existing phase. Than create new levels and link them to the new construction phase.

When you want to draw something, all levels are shown in the pull down menu behind the constraints and you have to scroll down to find the levels you want to use.

When you're in a view with the new construction phase, the levels from the existing phase should not be shown in the pull down menu behind the constraints, so you do not have to scroll past all levels.

Advocate
Advocate

I like the idea, mainly for the fact that where we have an existing building, not all of the levels will be retained/are relevant in the proposed phase.

Advisor
Advisor

You'd probably want the phases shown in the pulldown to be based on the phase(s) of the element.

Contributor
Contributor

I would like to have the simple option to add phases to my Grid Lines.

 

We have a lot of projects that exist of expansion of a building, and therefore we have existing grid lines and new grids for the expansion.

 

The workaround for now is to hide every grid manually per view, which takes unnecessary time.

 

 

 

Collaborator
Collaborator

There is also the issue of duplicate numbering - typically both existing and new projects have grids 1, 2, 3, a, b, c, etc.  I've added an "e" prefix before existing grids to get around it before, which also allows me to filter them, but it isn't a BIM solution.

Collaborator
Collaborator

My existing grid lines are different then the new ones so its easy to set visible or not

our work around voor the gridnumbers is to ad a dot 1. 2. etc.

Anonymous

If it is a new building, couldn't you just link in the existing building?

 

If it is an addition, can't you use filters to hide all gridlines less than 8, for example? Unless the issue is duplicate grid names as discussed above.

Collaborator
Collaborator

The project I had already had two sets of grids in the "Existing" scope, modeled as a single model. Unless the grids are on a separate workset or are a different family type you can't filter them, and the revit link "custom" option isn't granular enough (I usually want everything else to be "By Host"

Advisor
Advisor
Advisor
Advisor

You would think it would be easy to add Phase parameters to Grids and Levels, but extra logic would need to be added for the duplicate names. Would Revit just ignore duplicates? or would it have to manage them (to make sure they don't exist in the same phase - or at least don't "remain" in the same phase)? Current WORKAROUNDS: create different Types and use Filters (for phasing); add invisible characters (such as ZWNJ) to names (for duplicates).

Anonymous

Levels and Grids should have phasing options. We do a lot of phasing with existing buildings and the ability to phase the existing/previous levels and grids would be very helpful. We currently use worksets as a work-around but its cumbersome at best.

Participant
Participant
Enthusiast
Enthusiast

In "real life", existing grids (structure) stay, and new grids (structure) will be created. So why in Revit it doesn't works as well as the rest?

 

For now, we change the grid's bubbles so that the existing ones are filled with gray and the new ones are not filled but they appear in all the project phases, as they shouldn't.

 

Thank you for considering my idea :cara_con_una_leve_sonrisa:

Advisor
Advisor

 I agreed.

 

Meanwhile, we use a different family symbol for the existing grids, but that's just a workaround. I would also add that previous grids and new grids could sometimes  have the same numbering, which is not allowed in Revit. Once again, there is workaround for this, but this should be supported by Phases attribute.

Explorer
Explorer

I usually put the separate phases of grids on separate worksets and shut off the visibility of a particular workset in visibility graphics. Works for view templates or individual views. Phasing the grids would be faster, but this is an ok work-around.

Explorer
Explorer

Possibility to use different levels per phase.
For example, different height of roof top between existing and new.

Agree with this. +1. No update in 5 years. Why cant grids be phased just like the element its representing (the structure for example)

Explorer
Explorer

Working on renovations, it's common to have a set of levels for the existing phase and a new set of levels for the new construction. These end up clogging elevations and sections unnecesseraily. Adding phase parameters to levels would allow quick management of which levels to show on each drawing, saving a lot of time.

Advocate
Advocate

In our firm we use filters based on leveltype (we have level types for existing and new) .

But having the option to use a phase parameter would be great, would make at least two filters unessecasry wich is nice.

Advocate
Advocate

"add invisible characters (such as ZWNJ) to names (for duplicates)"

How-zat!?

Collaborator
Collaborator
Collaborator
Collaborator
Advocate
Advocate

How is this not available yet?

Collaborator
Collaborator

How do you solve the problem of when the existing level changes its datum ht e.g. when raising a house @benschilders and @nicola_peccin?

Advocate
Advocate

@Mark_Engwirda  If the whole house would need to be raised i think i would op to 
change the elevation of the project base point since the levels reference to that base point 

benschilders_0-1666860321342.png

 

Change project base point: 
1. activate project base point (make the subcategory of site project base point visible) 
2. select project base point on a floorplan
3. change elevation to desired raising height.

benschilders_1-1666860487189.png


Disclaimer:
This is how i would do this , maybe there are better ways of doing this. 

Contributor
Contributor

Phasing would be easier... To avoid different grid designation formats, I worked around this by duplicating the grid family type and adding "New" to the type name and filtering by type name.  (i.e. ' 1/4" Bubble ' and ' 1/4" Bubble (New) ') Does the same thing as the work set solution, but if you're not using/haven't enabled work sets...

Enthusiast
Enthusiast

Over 6 years on and this very sensible idea has not been added? It seems like it could be straight forward and would add so much utility for those working on renovation projects.

Enthusiast
Enthusiast

When working in a renovation project we now have to make separate level and grid types to hide them when working in existing / new. We would like to be able to demolish level and grids.

When modelling elements this would mean that, when for example a wall is modelled in the phase new only the levels that exist in the new phase show up.

Enthusiast
Enthusiast

Oké so the idea allready existed. Will there be any action taken?

Participant
Participant

It's been EIGHT years, please, Autodesk, make this change happen already. For phasing, object styles blocks any attempt to make this user friendly using the tools we DO have in our arsenal. The next best option is a filter per view / view template to force the override based on family / type name. And that still doesn't solve the issue raised by everyone above me on this thread - that a demolished gridline or level is just NOT possible and has to be hidden.