My construction project is a tenant build out for 80% of an existing building shell... the rest is FUTURE.  We must set space aside in our equipment room for Future equipment serving the future 20% that may or may not happen.  That space must be accounted for in the Current Phase.  We draw in equipment and plan out where duct and pipe connect, but we want it represented different from the current phase, and we don't really want duct or pipe to influence the current phase duct and pipe. 

 

So the equipment itself could be shown dashed in the current phase, and solid in the future phase.  Perhaps we want it invisible in the current phase, and solid in future.  Piping and ductwork in the current phase should remain intact, but in future show tees with segment breaks (plus whatever portion that was demolished to insert the tee).