@ipseluteWhere did you find the link to that file? Good try... but doesn't work (for draw order).

 

Dragging the view from the Sheets section of the Project Browser IS a good tip to re-place a view on a sheet, but it's only that: RE-placing the view. It saves you from having to remove the view from the Sheet and hunt it down in the Project Browser so you can add it back again, so thanks for that! But you have to manually reposition it (not a BIG issue if you can snap to another view) AND the View Title (position and line length).

 

@AnonymousYes, pyRevit > [Drawing Set] > Sheets > Reorder Selected Viewport can help. It's better than the above because it positions the view for you, but it's only a partial solution because it can't re-position the view title due to an API limitation - vote for Open up View title in Revit API to fix that.