Comentario
07-26-2023
04:20 PM
07-26-2023
04:20 PM
When editing wire paths it is not possible to select cable containment (tray and conduit), instead we must drag by eye the wires to the containment. If the containment used for wires could be selected to automatically edit the path, it could simultaneously add an association on each tray as to what cables it contains. I don't think creating full detail section views will be at all simple, but at least if a schedule could be put on the sheet the person editing the layout detail would have good information. The reason it would not be simple is that separation not only depends on cable size and load, but also classification of load type, sometimes this is a security thing (e.g. secret vs classified).