Show cycle time/work time in the Insert production screen

Show cycle time/work time in the Insert production screen

We can see the 'cycle time/work time' while we are in the Worker screen, but once you insert production (say, for example, just to fill in some data of the components, not because the operation is done) you cannot see the cycle time/work time unless you get out of the production screen. In that case, you lose the data.

 

It would be really helpful being able to see the time whether you are in the worker screen or you inserted production.

Another possibility is not losing the data, having the option of not just Cancel insert production but also EXIT (without losing data previously registered).

3 Comments
andrade_david
Autodesk
Status changed to: Gathering Support

Thank you for posting this idea, @aalmagroTJ9YP, I've marked it as gathering support.

In the meantime, could you give me more context about what you mean by "just to fill in some data of the components"? Is this about registering consumptions?

aalmagroTJ9YP
Explorer

Hi, yes, I'll explain it a bit more: when we produce, we start an operation in Fusion and also follow a technical report where we note down model of the components, serial number, the results of the measurements performed, etc.  In order to do it at the same time, in Fusion and our report, we "Insert production" at an early stage of the development of the operation and register in Fusion every detail we register in our technical report. This leads to the situation in which we produce the operation without being able to observe the working time, unless we cancel "insert production" and check the time in the worker screen. However, doing that would lead to the data previously introduced being deleted. This is why we suggest having a way to check the working time while the worker is inserting production, or having an option different from cancel so that we can get out of "Insert production" without losing the data.

andrade_david
Autodesk

Thank you, @aalmagroTJ9YP .

We'll consider this suggestion. In the meantime, there's this idea with a high count of votes (top 5) that is related to this problem. I'm saying this because we are considering not only allow to view PDFs and see a checklist at the same time but also to add consumptions on the insert production button while production is running (without having to necessarily click insert production to add that data).

If you comment this additional request there other users can also see and comment it.