Note the position of Sketch 4 in your timeline, it is after Sketch 3. So if you edit a sketch, created before, the sketch you want to project, it does not exist yet. If you can, left click and drag Sketch 4 to the left of Sketch 3 and see if this helps. This may not be possible depending on dependencies, I cannot tell since you did not attach your model. The timeline represents your sketches and features in time.
John Hackney, Retired
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.