Preempting for unloading from conveyor

Preempting for unloading from conveyor

MM_GZY
Explorer Explorer
128 Views
0 Replies
Message 1 of 1

Preempting for unloading from conveyor

MM_GZY
Explorer
Explorer

I am working on a large model and am stuck at the stage of unloading products from the conveyor.

Operators work on the conveyor at DP's, and when the product reaches the end of the line (last DP), operators from stations 2 and 3 are supposed to approach and unload the product onto a pallet, then return to their stations and continue working on the products they left behind.

The problem is that when the first product is removed from the conveyor, the logic works as intended. Still, with the second product, the operators do not interrupt the task, but first finish it and only then remove the second product from the conveyor, and with the third product, they only approach it.

 

What are the possibilities for the process flow to work as it did with the first product?

Many thanks for considering my request.

 

0 Likes
129 Views
0 Replies
Replies (0)