Control point deallocate on continue

leo_l6
Not applicable

[ FlexSim 22.0.16 ]

Hi,

Is there a way to enable deallocate on continue for AGV network control points? The goal is for an AGV behind another AGV to start moving as soon as the one in front starts. "Deallocate When Past Current" requires the one in front to clear the control point before it's deallocated which doesn't work.

0 Likes
Accepted solutions (1)
125 Views
1 Reply
Reply (1)
Message 2 of 2

Jeanette_Fullmer
Community Manager
Community Manager
Accepted solution

Hello @Leo L6,

You can adjust the Deallocation Types in the AGV Network in the tool box.

1695929788720.png

In this case changing the Center to Leading edge may work for what you want