Charts Not Populating Data

Charts Not Populating Data

josdijf23948
Not applicable
204 Views
4 Replies
Message 1 of 5

Charts Not Populating Data

josdijf23948
Not applicable

[ FlexSim 24.0.2 ]

Hi everyone,

I am following the tutorial basics and for the most part, I think I am done..

Reference: https://docs.flexsim.com/en/20.2/Tutorials/FlexSimBasics/1-2GetData/1-2GetData.html

However, some of my charts don't work, even though I followed the steps exactly.

1736476019686.png

It would be much appreciated if you could point out what went wrong and help me set them correctly! 🙂

TutorialBasics.fsm

0 Likes
Accepted solutions (1)
205 Views
4 Replies
Replies (4)
Message 2 of 5

moehlmann_fe
Advocate
Advocate
Accepted solution

After swapping the model to Process Flow the customers do not enter the 3d sinks anymore, which is why the Throughput and Happy vs Unhappy chart do not display anything, since they read the input statistic of those object. You can swap them to instead get the statistics of the PF sinks.

Similarly the service desks are now only props and do not change their state anymore. Thus the Utilization chart only shows them as idle. You can 'manually' set their state through a pickoption in the Custom Code activity in Process Flow if you want (Control -> Set Object State).

0 Likes
Message 3 of 5

josdijf23948
Not applicable

Hi! Thanks for reply.


I think I get what you are getting at..

"You can 'manually' set their state through a pickoption in the Custom Code activity in Process Flow if you want (Control -> Set Object State)."

Could you show me a screenshot or video of those steps you described? if you could help me change it to make it work the way you said, that would be great too 🙂

0 Likes
Message 4 of 5

moehlmann_fe
Advocate
Advocate

Before and after the delay that represents the process time, set the state of the respective service desk to "processing" and then back to "idle".

capture1.png

tutorialbasics_1.fsm

0 Likes
Message 5 of 5

josdijf23948
Not applicable

Thanks for your help! I managed to get the data I needed for the other 2 charts too but there's is one small issue.


1736516363795.png
Is there a way to change the chart label to be different from the process label while maintaining the process data?

I don't need the whole process path, just "Happy Customers" and "Unhappy Customers"

TutorialBasicsDone.fsm

0 Likes