Hello all,
I have a process flow and 3D model. I have 2 types of items which their interarrival are unifrom. with the UR the items are processed and each item put in separate Queue (station 1 &2) then task executer comes to grab the items and put on the other stations. in process flow as it is visible I have 2 decision for adjusting the speed of UR. one is based on interarrival then based on the items that I have in the last stations(3,4). each item would remain in the stations 3 &4 just for 300 seconds then they will be sink. how I can have a synchronize process flow and 3D model. now they are not sync.
I have uploaded my model. I appreciate if you could help me.