I'm guessing the answer is a simple setting that I'm missing, but how can I get my parcel map check to run counter-clockwise? The stubborn thing insists on going clockwise. In the Analysis tab of the Parcel Properties dialog I've tried checking the 'Process segment order counterclockwise' box but it doesn't stay checked after exiting the dialog. In the Create Reports - Parcel Mapcheck Report dialog there is a box for 'Process segment order counterclockwise' but it's greyed out so I can't access it. If it helps any I have C3D 2019 on Windows 7.
Thanks,
Renee