I am looking for help to calculate the mass haul quantity for a 10 km long roadway. Our existing ground is quite hilly, so the mass haul diagram is very up-and-down.
I can find loads of tutorials to create a mass haul diagram, but nothing on calculating the quantity of haul.
In my jurisdiction we pay for haul based on the m3hm or, cubic meter hectometer. This is volume of earth hauled 100 meters. This equals the area under the mass haul line or more descriptively, the area between the mass haul line and the zero line.
Any point along the mass haul line will give the amount of material that is in transit at that specific spot, but haul isn't JUST a volume is it? I could haul 40 m3 of earth 1 km or 10 kms and I would want a different amount of money for each of those operations. To find that I need the area under the graph, not a volume.
We always manually calculate the area under the graph with bpoly, picking the internal point to create the closed polyline, viewing the properties of that closed polyline to get the area, making some conversions to account for vertical and horizontal scale, and then adding up all the individual areas (there will be multiple areas – one for each portion of the line as it goes above and below the zero line as shown in the attached photo) for the total amount of haul to pay for the project. This total amount of haul is then what goes on the bid form for the project for the prospective contractor to base his/her bid on.
Is there a way in C3D to find this total number?
Edit: I forgot to mention, the method I outline above works, but it is too labor intensive to do it over and over whenever a corridor change is made. Something dynamic would help immensely.