P&ID calculated properties

KenFoysterWSP
Contributor

P&ID calculated properties

KenFoysterWSP
Contributor
Contributor

Hi,

I have created several P&ID Off-Page connectors (OPC) calculated properties, to overcome a limitation of the product when building the OPC blocks.

The calculated properties work very well at placement/connected to a line; the issue is when a property used to build the calculated property is changed. The property value does not update automatically. 

Is there a way to automate the update of the values? Currently the only way is to disconnect and reconnect the OPCs.

0 Likes
Reply
Accepted solutions (1)
158 Views
3 Replies
Replies (3)

h_eger
Mentor
Mentor

@KenFoysterWSP ,

 

I think you should achieve your desired result with the ‘PLANTREFRESHACQPROPERTY’ command.

But be careful if you run this function over the whole project, you should have a cup of coffee, it might take a few minutes.

 

08-02-2025_08-47-15.jpg

-

If my reply was helpful, please give a "Kudo" or click the "Accept as Solution" button below (or both).

Hartmut Eger
Senior Engineer
Anlagenplanung + Elektotechnik
XING | LinkedIn

EESignature



0 Likes

KenFoysterWSP
Contributor
Contributor

Thank you for your response. The solution works well to update the acquisition values.

After further investigation, I have noticed the visual representation of the values in the OPC is not updating, despite the value being correct in the properties panel. It is as the block is not updating or refreshing. Can this be forced or automated?

Note: the Page Connector From is a calculation.

 

SAW - Connectors.jpg

0 Likes

h_eger
Mentor
Mentor
Accepted solution

https://help.autodesk.com/view/PLNT3D/2024/ENU/?guid=GUID-51FC4575-D9ED-42A0-BC5D-24DB8D51CE5F

-

If my reply was helpful, please give a "Kudo" or click the "Accept as Solution" button below (or both).