I'm an advanced Solidworks user, but very new to Autocad. I'm looking for some best practices on drawing a very simple manufacturing floor plan. I have the major dimensions, but now I'm looking for best practices on how to draw/import my machines onto the floor. I.e. I'm wanting to draw the machines separately and import them into the main file so I can play with their positions on the floor. The machine drawings will be simple, 2D drawings that just show the machine footprint. 

0 Me gusta
Responder
Soluciones aceptadas (2)
1.103 Vistas
8 Respuestas
Respuestas (8)

Patchy
Mentor
Mentor

If the machine drawing is .dxf or .dwg just use the INSERT command after you have the floor plan drawing setup with the same unit (Metric or Imperial)

0 Me gusta

pendean
Community Legend
Community Legend

@brad_walkerLEUWS Are you by chance just using plain AutoCAD (the topic of this forum) or one of the verticals that might be better suite for your need (free for subscribers to install and use by the way)

pendean_0-1701357921293.png

 

 

0 Me gusta

RSomppi
Advisor
Advisor

@brad_walkerLEUWS wrote:

I'm wanting to draw the machines separately and import them into the main file so I can play with their positions on the floor. The machine drawings will be simple, 2D drawings that just show the machine footprint. 


Those could be blocks or XREFs that can be inserted into the "main file".

0 Me gusta

Washingtonn
Collaborator
Collaborator
Solución aceptada

Best practice:

Create blocks and/or Xrefs which include the actual footprint, anchorage locations and the extreme outside dimensions.  Indicate height clearances (attributes?) if this might be an issue and include all separate layering needed to identify clearances for operators, maintenance, service connections for the installation, operation and maintenance workers.

Don't forget to verify paths for removal/installation involving equipment which may need to be replaced.

0 Me gusta

brad_walkerLEUWS
Participant
Participant

I'm just using "regular" AutoCad. Would you prefer one of the ones you pictured above the other for this application?

0 Me gusta

brad_walkerLEUWS
Participant
Participant

Thank you for your reply. Excuse my ignorance here, but is one of those methodologies easier to move the machines around within the floor? That's my main concern. I know we'll be moving the machines around a lot brainstorming best options. 

0 Me gusta

pendean
Community Legend
Community Legend

@brad_walkerLEUWS wrote:

I'm just using "regular" AutoCad. Would you prefer one of the ones you pictured above the other for this application?


That's a question only you and your employer can answer: install them and explore.

0 Me gusta

RSomppi
Advisor
Advisor
Solución aceptada

Personally, I would use blocks as I think most would but XREFs are a viable option.