When I use joint copy on the cleats i have added to the rafters its placing the cleat on the wrong side of my purlin? New to Advance so not sure if I'm doing it wrong!
0 Likes
Reply
Accepted solutions (1)
387 Views
2 Replies
Replies (2)

múinteoir
Advisor
Advisor
Accepted solution

If you are talking about the cleats for cold rolled purlins, this is due to the way the purlins are added to the roof. When added you are picking from left to right or right to left, this selection contols the orientation of the cleat. I think that when you copy the cleat accross the rafters were defined in the opposite way so therefore the cleat goes on the wrong side. Please attach a drawing as it may not be this reason.

 

Forum Signature.png

The face of the BIM game | Former Autodesk Expert Elite | YouTuber | Lego Builder | Monaghan Man | Some Can, Some Cant

Anonymous
Not applicable
Thanks that seems to have solved my issue