I required views like in transmission line tower industries.

I required views like in transmission line tower industries.

avinash00002002
Collaborator Collaborator
785 Views
3 Replies
Message 1 of 4

I required views like in transmission line tower industries.

avinash00002002
Collaborator
Collaborator

As per our industry We make tower from L shape angle and we required views 2D drawings views from 3D drawings as per attached images. How to do setting in AS.

0 Likes
786 Views
3 Replies
Replies (3)
Message 2 of 4

Anonymous
Not applicable

Hi @avinash00002002,

 

first, if you want to create Transmission towers in AS, you need a minimum basic course in AS, preferably also advanced training (processes, drawings, parts lists, ...) - please contact your local reseller. Without these course, you will not be able to move on. When you have finished the courses, you can only start thinking about what and how, because you will be able to 😁.

 

Transmission towers are special constructions, mostly without parallel connected parts, currently there is no parametric module for such constructions in AS - a lot of manual work, which, however, can be automated with a certain degree of knowledge and experience. 

 

With a certain time shift, you will then be able to create something similar - until then, you have to learn, learn, learn (said Lenin in his time in Russia):

Part.png

 

Part 1.png

 

 

Message 3 of 4

alickomay
Collaborator
Collaborator

angles like u show are essey-ish to automate the drawing out put so that thay need no clean up

the asembily drawings take a lot more work 

use weld/bolt location "site and shop" to control how big assembly drawing are (make sub asembily drawing)

 

all thow i dont agree u will not be able to move forward  with out  training , as meny user have no training 

but u will need to educate your self sum how , youtube ,books.this site - search for old questions 

 

 

0 Likes
Message 4 of 4

Anonymous
Not applicable

@alickomay  schrieb:

angles like u show are essey-ish to automate the drawing out put so that thay need no clean up

the asembily drawings take a lot more work 

use weld/bolt location "site and shop" to control how big assembly drawing are (make sub asembily drawing)

 

all thow i dont agree u will not be able to move forward  with out  training , as meny user have no training 

but u will need to educate your self sum how , youtube ,books.this site - search for old questions 

 

 


You will need much more time to do this to master the more complex things that a person will actually learn in the course. Therefore, in this forum there are questions of a very basic (and important) character, which you will automatically learn in the course. It is best to look for only special problems in the Youtube / forum. If you want to make advisory progress and not expect an x-year, the above courses are more than recommended (you don't spend much more time searching the internet, but you actually work at Advance Steel). If I take into account special constructions, such as transmission towers (which, by the way, I have been drawing for many years), you have to expand your repertoire with other methods and procedures that you come up with yourself - sometimes you feel like David Copperfield 😁.

 

Everything you do now will affect your near and distant future. And what can you do now, don't put it off until tomorrow.