Schedule & Primavera P6 - Physical % Complete

Schedule & Primavera P6 - Physical % Complete

We do our scheduling program in P6 and then upload it into ACC Schedule once a week but the "% complete" column does not correlate to "Physical % complete" and I already know it only translates "Duration % complete" correctly. The reason why we are and want to use the Physical option is we can write the percentage manually, but the Duration option is a fixed formula with respect to current date, start date and finish date.
My feature request is: Is it possible to add the usage of "Physical % complete" in ACC Schedule? so that it correlates correctly into "% complete"?

5 Comments
kevin_scottMTSYW
Community Visitor

Can a column be addednto ACC that indicates the actual physical % complete in ACC

Dyrmundur_Helgi
Contributor

That would be great @kevin_scottMTSYW but I don't think it is possible as is... maybe it is possible as a additional field within a activity. Not sure how that would work though.

Essential feature. Please priorise. Kind of show stopper today.

mohit_jainXER6C
Community Visitor

Have you found the solution, please let me know...

Dyrmundur_Helgi
Contributor
Hi, no I haven't got any response from Autodesk on this one. This bug is a huge problem for us still and I do not understand why this has not been addressed or fixed.