Currently the RFI tool does not allow you to have a "Submitted On" date, and only has "Created On", "Updated On" and "Closed On". The date that the RFI was actually submitted is the most important to us when tracking how long an RFI has been in the reviewers court. There are a lot of times when there is a lag between when an RFI draft is started versus when it is submitted to the reviewing party.
As an example below. You can see that this RFI moved out of the Draft to Review stage on 8/11/2025, however the only date we can get to show on the RFI log is the date the draft was created on 8/7/2025.