Currently there are uncountable limitations in the cost management module. If possible, I would like to break them down and hope from Autodesk Team to solve them as soon as possible as these are already hurting operations.
Budget:
1- Budget limitation of 10,000 budgets per project. Most mega projects have at least 5000 Bill of quantities line items. Just imagine the number of budget line items associated to those. make the limit to be at least 50,000 budget line items.
2-Budget subitems. Currently budget sub items follow the hierarchy of the budget line item, what is need that the subitem to have fixed classification code as its main item, or to have at least the option to make it available from the account admin.
3- Mapping budget to BOQ line item in SOV of the main contract. What the system is missing is a better way to have a direct and easy comparisons between BOQ selling/ Budget / Cost. linking them (as sum(if)) in excel would make the software applicable to use.
4-Importing Custom Attributes. I don't know about this but having to use APS or manually entering Mutiple custom attributes for Mutiple budgets/contracts doesn't make the cost management module applicable to use, also having the ability to have calculations on numeric field in custom attributes is a must.
There are many needed customizations needed for the cost management module, but I think from my perspective that those are the most needed to be applied right now.