I have an existing project that I now need to split into 2 package phases, per the client. How can I copy the entire project in Vault? I know I can use "copy design" for an individual file, but I want to duplicate the whole project. Thanks.
Solved! Go to Solution.
Solved by john.laidler. Go to Solution.
You can use 'copy design' for an entire project.
Where? That option is grayed out under "edit" when I click on the project folder.
You 'Copy Design' multiple files.... not a 'project file'.
If I have a surface, pipe network, etc. referenced into the files, will all the copied files reference the new project then? Or still the old project?
Depends on what you want.
REUSE = Keep old referenced files
COPY = Copy Reference, and re-link to new Parent Copy.
When I select "copy design" the option does not even come up to include the referenced files, as well. "include attachments", "include dependents" and "include library files" are all checked. What am I doing wrong?
I want to copy the referenced files, not re-use them, and I am using 2010.