Hi,
I want to do combined footings.. I select 2 points and go to "provided reinforcement of RC elements" and sometimes define a comon footing with two columns and sometimes no... they have 5 m. What can I do when it define 2 footing instead one footing. why sometimes yes and sometimes no...
one can try with and industrial building made with the aistant for load and geometry by Robot. Later you select two nodes and made 2 footings
Thanks
This depends on the selected dsign code and geomtery (e.g. rotation) of columns.
If you find your post answered press the Accept as Solution button please. This will help other users to find solutions much faster. Thank you.
The standards are the BS Eurocode standards..
There is no solution? if RSA don't select combined footing for this standard we can't do anything?