Rounding Up People

293 Views, 1 Replies
06-15-2012 04:43 AM

Is there a way to specify people or calculation people to where the value gets rounded up?  I cannot find it in the Project Units, and I cannot make changes through the Schedule...

Adrianna Schneider, LEED AP
AEC Solutions Engineer

:

Please mark Accept as Solution if your question is answered. Kudos gladly accepted.

I believe the best you can do is create a Calculated Value (Number) in the schedule with the formula "roundup(Number of People)". That would make it display cleanly, but would not at all affect the calculations.

*Expert Elite*
3,480 Posts
997 Kudos
Registered: ‎08-28-2009
Post 2 of 2

Re: Rounding Up People

06-15-2012 05:43 AM in reply to: aschneider1

I believe the best you can do is create a Calculated Value (Number) in the schedule with the formula "roundup(Number of People)". That would make it display cleanly, but would not at all affect the calculations.

Corey D.                                                                                                                  ADSK_Logo_EE_2013.png    AutoCAD 2014 User  Revit 2014 User
──────────────────────────────────────────────────────────────────────
⁞|⁞ Please use Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos as appropriate to further enhance these forums. Thank you!