Pipe Tags cannot be scheduled

Hi Guys,

 

Revit MEP can tag end offset and start offset of the pipes, but cannot schedule them, any ideas?

 

I actually need to schedule the start and end offset of the pipes, this can be done through spot elevations as well but this cannot be scheduled as well.

 

so if i can schedule either end/start offset or the spot elevations i would be good to go!

 

thanks for the responses in advance.

1 REPLY 1
Message 2 of 2
L.Maas
in reply to: Anonymous

Unfortunately this will not be possible. Offset can not be scheduled.

As tags are only reporting other family values they can not be sheduled as they hold no values themselves.

 

The only solution would be to add project parameters to the pipes category and fill them manually with the offset values.

However you would have to manually update the values if the offset of the pipes change, so....

 

Maybe that something could be programmed through the Revit API?

 

 

Louis

EESignature

Please mention Revit version, especially when uploading Revit files.

Can't find what you're looking for? Ask the community or share your knowledge.

Post to forums  

Autodesk Design & Make Report


Autodesk Design & Make Report