Hey so I was wondering how do I get the bottom height of the pipe to be correct? For example, when I put in a 8" diameter pipe at an offset of 8.63' (I have set the justification to bottom) I measure the bottom of the pipe and it will show as 8.262'

 

So my question is, how do I make the pipe specify the correct height that I want from the bottom of pipe to the grade level?


DaraWC wrote:

"Hey so I was wondering how do I get the bottom height of the pipe to be correct? For example, when I put in a 8" diameter pipe at an offset of 8.63' (I have set the justification to bottom) I measure the bottom of the pipe and it will show as 8.262' "


The Justification of the Pipe or Duct does not dictate it's placement - it's more for aligning different sizes of Pipe across Transition Fittings as depicted in the image below.

 

PipeJustification.JPG

 


DaraWC wrote:

"So my question is, how do I make the pipe specify the correct height that I want from the bottom of pipe to the grade level?"


I think the way to accomplish this is to create a dimensional constraint between the bottom of the Pipe (that's already drawn) and the grade level. That will keep the bottom of the Pipe at that exact elevation should the Pipe's size change. There's no real great way to do this.

*Expert Elite*
CADastrophe
Posts: 3,421
Registered: ‎08-28-2009
Message 2 of 2 (582 Views)

Re: MEP pipe elevation height problem

08-30-2013 12:50 PM in reply to: DaraWC

DaraWC wrote:

"Hey so I was wondering how do I get the bottom height of the pipe to be correct? For example, when I put in a 8" diameter pipe at an offset of 8.63' (I have set the justification to bottom) I measure the bottom of the pipe and it will show as 8.262' "


The Justification of the Pipe or Duct does not dictate it's placement - it's more for aligning different sizes of Pipe across Transition Fittings as depicted in the image below.

 

PipeJustification.JPG

 


DaraWC wrote:

"So my question is, how do I make the pipe specify the correct height that I want from the bottom of pipe to the grade level?"


I think the way to accomplish this is to create a dimensional constraint between the bottom of the Pipe (that's already drawn) and the grade level. That will keep the bottom of the Pipe at that exact elevation should the Pipe's size change. There's no real great way to do this.

Corey D.                                                                                                                  ADSK_Logo_EE_2013.png    AutoCAD 2014 User  Revit 2014 User
──────────────────────────────────────────────────────────────────────
⁞|⁞ Please use Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos as appropriate to further enhance these forums. Thank you!
Post to the Community

Have questions about Autodesk products? Ask the community.

New Post
Announcements
Do you have 60 seconds to spare? The Autodesk Community Team is revamping our site ranking system and we want your feedback! Please click here to launch the 5 question survey. As always your input is greatly appreciated.