Lights hosted in a linked RCP plan, If they move do I have to recircuit them?

1 REPLY 1
Reply
Message 1 of 2
Jason_S
228 Views, 1 Reply

Lights hosted in a linked RCP plan, If they move do I have to recircuit them?

I have been asked to shift some lights in my model.  They are shifting a couple inches and some are rotating 90 degrees.  Will I have to recircuit these lights? 

 

They are hosted in the RCP of the Architectural model.  Revit MEP 2012.

 

Thank you.

 

1 REPLY 1
Message 2 of 2
CoreyDaun
in reply to: Jason_S

No. Unless you have to change a parameter that affect it's electrical settings (i.e. Voltage), it should maintain it's connection to the circuit. Even if re-hosting it should be fine.

Corey D.                                                                                                                  ADSK_Logo_EE_2013.png    AutoCAD 2014 User  Revit 2014 User
──────────────────────────────────────────────────────────────────────
⁞|⁞ Please use Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos as appropriate to further enhance these forums. Thank you!