Chiller Plant - getting the piping system to work

1391 Views, 2 Replies
02-05-2010 07:14 AM
I have watched the videos of Inside the System Go with the Flo and I can get a simple layout to work. What I am struggling with is getting a "real world" chiller plant to work.

There are 3 chillers (all the same), 3 cooling towers (all the same), a drain down pit, and 3 pumps (all the same).

I am trying to figure out what combination of connector properties will work.

Additionally, how do you assign the pieces of equipment to the system. Which should be the children and what do you do about the fact that you can only have a single piece of equipment.

See the attached picture of the layout.

Anybody have any success creating a multi tower/chiller/pump system?

Thanks,
New Member
1 Posts
0 Kudos
Registered: ‎02-12-2010
Post 2 of 3

Re: Chiller Plant - getting the piping system to work

02-13-2010 07:42 AM in reply to: jbecker-vector
Hi...
jbecker-vector your question, your problem:
I have watched the videos of Inside the System Go with the Flo and I can get a simple layout to work. What I am struggling with is getting a "real world" chiller plant to work.
There are 3 chillers (all the same), 3 cooling towers (all the same), a drain down pit, and 3 pumps (all the same).
am trying to figure out what combination of connector properties will work.
Additionally, how do you assign the pieces of equipment to the system. Which should be the children and what do you do about the fact that you can only have a single piece of equipment.
See the attached picture of the layout.
Anybody have any success creating a multi tower/chiller/pump system?
Thanks,

My solution this for case:

Water icy:
Configuration for this system consist in pipeline for water icy, pumps water icy, all fittings.

Water condenser:
Configuration for this system consist in pipeline for water condenser, pumps water condenser, all fittings

All Consist in two systems separate: pipeline for water icy, pumps water icy, all fittings, fancoils. -- pipeline for water condenser, pumps water condenser, Towers, all fittings

all systems are closed systems

it is necessary to send complete project in AutoCAD generico.
I await your request.

lcchvacr... design and projects Mep systems.
Contributor
12 Posts
0 Kudos
Registered: ‎11-29-2011
Post 3 of 3

Re: Chiller Plant - getting the piping system to work

11-29-2011 01:53 AM in reply to: lcchvacrmep

I have the same proplem but my chillers plant consists of 6 air cooled chillers and 4 pumps. I can inspect the system up to pumps and the total flow is correct but the flow thru pumps is zero and also thru the pump header and all pump fittings all the flow is zero. In addition to that, the flow thru chillers is zero also, only the flow thru the main pipe of fan coil units is correct.

Please any help in this matter

 

ghassan76ha@yahoo.com

Post to the Community

Have questions about Autodesk products? Ask the community.

New Post
Announcements
Are you interested in helping shape the future of the Autodesk Community? To participate in this brief usability study, please click here. Your time and input is greatly appreciated!