We started the Revit Architecture model before we had actual elevations from a survey so we could do a test fit, etc.
The first floor was put to 2'-0" above the project base point, which would be the approximate location of the sidewalk.
Now That we have survey elevations I know that the first floor is more like 33'-0". I cannot move the project base point relative to the model, so I moved the survey point down 33'. Now I can get my level markers to read relative to sea level or to the project base point (i.e. sidewalk), but I can't input survey points to generate the topo. The survey points should be relative to sea level, but the only option I have input them relative to the project base point.
I can't select and move everything manually in the project up 33', because the model is too far along.
As a workaround, I've decided to just make the topo and then manually move that down 33', but please let me know if there is a better way.
Thanks
Attached a image that explains the procedure