Hello guys,

 

Maybe you could help me with this, I tried so many times but i cannot get exact one.

 

1)how to combine the total area of URA-_RF_ROOF LEVEL into one from Production OL_Area. (formula need)

2) how to combine the total area of URA-_RF_ROOF LEVEL into one from Roof OL_Area.(formula need)

3) how to divide area from URA-_FP_1ST STOREY LEVEL (1491.21 / 10 /10 ) so that i can get occupany load (no. of person) per unit.

 

Thank you very much.

For items #1 and #2, you will have to adjust your Schedule's Sorting/Grouping and uncheck "Itemize Every Instance", and then go to the Formatting tab, select those Fields and enable "Calculate Totals".

 

For #3, you will need to create a Calculated Value. Note that you cannot create calculation based on the Total Area - the calculations will be made for each individual area and then the results totaled.

*Expert Elite*
3,492 Posts
1,001 Kudos
Registered: ‎08-28-2009
Post 2 of 3

Re: Revit 2014 Need help some formula in calculated values

12-23-2013 05:25 AM in reply to: ennujozlagam

For items #1 and #2, you will have to adjust your Schedule's Sorting/Grouping and uncheck "Itemize Every Instance", and then go to the Formatting tab, select those Fields and enable "Calculate Totals".

 

For #3, you will need to create a Calculated Value. Note that you cannot create calculation based on the Total Area - the calculations will be made for each individual area and then the results totaled.

Corey D.                                                                                                                  ADSK_Logo_EE_2013.png    AutoCAD 2014 User  Revit 2014 User
──────────────────────────────────────────────────────────────────────
⁞|⁞ Please use Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos as appropriate to further enhance these forums. Thank you!
Valued Mentor
445 Posts
27 Kudos
Registered: ‎10-08-2007
Post 3 of 3

Re: Revit 2014 Need help some formula in calculated values

12-23-2013 06:29 PM in reply to: CADastrophe

Thank you Corey D.