Hi

 

I have a project with many drawings with Preliminary Issues. We want to go to Construction on some of the drawings but not all.

When we go to construction we remove all the previous revisions as start again at C1.

Obviously we don't want to remove previous revisions from the project as they will still be on sheets that are not going out for Construction but just specific sheets. If we merge revisions then we will lose them from sheets that we don't want to send out for Construction.

 

What is the best way to go about this?

 

Many Thanx

 

Barry

 

 

Post to the Community

Have questions about Autodesk products? Ask the community.

New Post
Announcements
Are You Going To Be @ AU 2014? Feel free to drop by our AU topic post and share your plans, plug a class that you're teaching, or simply check out who else from the community might be in attendance. Ohh and don't forgot to stop by the Autodesk Help | Learn | Collaborate booths in the Exhibit Hall and meet our community team if you get a chance!