door schedule - keying in details

318 Views, 1 Replies
01-29-2013 10:36 AM

I've added the fields in my door schedule for head, jamb and sill details.  These field appear be manually completed.  Is there a way to link the field to the actual detail?  

 

That way, for example if the detail were to be moved to another sheet, the field in the door schedule would be automatically updated.

Active Contributor
kfielding
Posts: 36
Registered: ‎06-06-2012
Message 2 of 2 (284 Views)

Re: door schedule - keying in details

01-31-2013 12:55 AM in reply to: wpiotraschke

Unfortunately not.  This is still a manual process I am afraid. It isn't possible to reference other views within a schedule.

Kevin Fielding
BIM Manager, AEW Architects
Manchester, UK

If my post solves your issue, please accept this as a solution and give me a thumbs up!
Announcements
Are you familiar with the Autodesk Expert Elites? The Expert Elite program is made up of customers that help other customers by sharing knowledge and exemplifying an engaging style of collaboration. To learn more, please visit our Expert Elite website.
Need installation help?

Start with some of our most frequented solutions or visit the Installation and Licensing Forum to get help installing your software.