Good afternoon,
Is it possible to copy a phase from one level to the other. For example, on Level 1 I have walls that are Existing, Demo, and New Construction. If I select the objects and copy to clipboard and paste the objects to anotehr level they will all switch to New Construction. Is there any way we can have the walls remain the same phase when copied to another level?
Thanks in advance.
Phase is a property of the view. Set the other view to the required phase before pasting elements.