HI.
Is there a way to sync and release ownership of a single known element that has been modified back to the Central model without having to do a full Sync with central? In this case there has been a single modification to the keynote table through code. It would be much quicker if we could then reliquish that single element back to the central file.
Possible?
Solved! Go to Solution.
Solved by jeremytammik. Go to Solution.
Dear Phillip,
I am not an expert of these things, but I have heard often enough how hard it is for Revit to determine the elements affected by a change, any change at all.
On that basis, I will hazard a guess, and say:
No, of course not. Imagine the general case? A change to one single element might potentially affect the entire model. So you cannot sync in isolation.
That is the cost of a consistent parametric BIM, and there is no way around it.
I hope I am not too far out on a limb here...
Cheers,
Jeremy
Thanks Jeremy for your reply.
I thought as much but wanted to make sure I was not missing anything.
Regards
Phillip