When working in a milestone, what do the different colors represent?

148 Views, 1 Replies
01-30-2013 08:25 AM

When working in a milestone, what do the different colors represent?



John Hill
Support Specialist
Product Support
Autodesk, Inc.

The colors used in a milestone can be very useful when you take a quick glance and imediatley are able to identify what milestone needs attention.

 

Green

 

Milestone event awaiting.  The associated milestone event is on time with the target date,   and outside the warning days before period (if any).

 

Milestone event reached. Reached the associated milestone event on time, before 12 a.m. of the target date, and outside the warning days before period (if any).

 

 

Orange (occurs on milestones with warning days before only):

 

Milestone event awaiting. The milestone is close to being late. The date today is within the warning days before period.

 

Milestone event reached. The milestone was almost reached late. It reached the associated milestone event on or before 12:00 a.m. of the target date, but within the warning days before period.

 

In both cases, the +/- Days from Target Date shows as a negative (-).

 

 

Red

 

Milestone event awaiting. The milestone is late. The date today is later than the 12:00 a.m. of the target date.

 

Milestone event reached. Achieved the milestone late. Reached the associated milestone event after the target date.

Product Support
JohnCHill
Posts: 353
Registered: ‎03-27-2012
Message 2 of 2 (145 Views)

Re: When working in a Milestone, what do the different colors represent?

01-30-2013 08:41 AM in reply to: JohnCHill

The colors used in a milestone can be very useful when you take a quick glance and imediatley are able to identify what milestone needs attention.

 

Green

 

Milestone event awaiting.  The associated milestone event is on time with the target date,   and outside the warning days before period (if any).

 

Milestone event reached. Reached the associated milestone event on time, before 12 a.m. of the target date, and outside the warning days before period (if any).

 

 

Orange (occurs on milestones with warning days before only):

 

Milestone event awaiting. The milestone is close to being late. The date today is within the warning days before period.

 

Milestone event reached. The milestone was almost reached late. It reached the associated milestone event on or before 12:00 a.m. of the target date, but within the warning days before period.

 

In both cases, the +/- Days from Target Date shows as a negative (-).

 

 

Red

 

Milestone event awaiting. The milestone is late. The date today is later than the 12:00 a.m. of the target date.

 

Milestone event reached. Achieved the milestone late. Reached the associated milestone event after the target date.



John Hill
Support Specialist
Product Support
Autodesk, Inc.
Post to the Community

Have questions about Autodesk products? Ask the community.

New Post
Announcements
Do you have 60 seconds to spare? The Autodesk Community Team is revamping our site ranking system and we want your feedback! Please click here to launch the 5 question survey. As always your input is greatly appreciated.