Revision Pinning Question

1 REPLY 1
SOLVED
Reply
Message 1 of 2
sten
368 Views, 1 Reply

Revision Pinning Question

Is there a way I can pin a revision to the upcoming revision?

 

The need occurs when I have a Change Order where I am both releasing items and a BOM referencing those items.

 

 BOM unreleased -> A

      ITEM1   unrelease -> A

      ITEM2   unrelease -> A

      

From what I can see then I have to release all items hierachical from the lowest level and up and then apply pinning as I go.

 

Is there a way to get around this?

1 REPLY 1
Message 2 of 2
sten
in reply to: sten

Got response:
"At this point in time there is not away around this other than the way you describe."

Created new idea in ideastation:
http://forums.autodesk.com/t5/plm-360-ideastation/more-flexible-revision-pinning/idi-p/5362959