PM Tab Timeline - Unexpected Behavior

5 REPLIES 5
Reply
Message 1 of 6
Anonymous
367 Views, 5 Replies

PM Tab Timeline - Unexpected Behavior

I'm looking at the timeline on a PM tab and I see the green bar indicating status is proportioanl to the % complete and not the milestone reached. I would expect that when a milestone is reached the "green bar" woul align with the appropriate milestone.

 

2013-10-01_1327.png

 

My veiw is that I want to have a visual indicator as to where the items is in relation to dates and not % complete as as a Project Manager I'm terested in due dates over % complete.

 

This is not a big issue it's just seems a bit odd.

 

 

5 REPLIES 5
Message 2 of 6
bastien.mazeran
in reply to: Anonymous

Hi Orin,

This would be a great feature, please submit this as new idea in our IdeaStation website.

Regards,



Bastien Mazeran

Technical Support Specialist

Message 3 of 6

Hi Orin,

I would like to check something else with you. If you go to the task item and look at the milestones, is the % complete value set to 40 % for the milestone labelled [05] 50%? It could be that the milestone label does not match the % complete assigned to that specific milestone after all.

Regards,



Bastien Mazeran

Technical Support Specialist

Message 4 of 6
Anonymous
in reply to: bastien.mazeran

Yes it is.

 

I know it seems odd but the state [05] 50% represents 50% of engineering state complete but overall progress is 40%.

Message 5 of 6
bastien.mazeran
in reply to: Anonymous

Hi Orin,

Could you please post screenshot of milestones tab for that task item?

Regards,



Bastien Mazeran

Technical Support Specialist

Message 6 of 6

Hi Orrin,

Thank you for sending screenshot of task's milestones tab. The % complete on the task itself also shows 40 %, so there is no problem there. The milestones' bars are positioned based on dates and do not follow the % complete. Please log new feature request on IdeaStation website to have timeline follow dates data rather than % complete data.

Regards,



Bastien Mazeran

Technical Support Specialist