Just a quick question to see if anyone has some insight. Is there a reason why I am not able to derive "Dates" from workspace to workspace, but other than "Dates" for a field type I can?
Thank You,
Hi Trevor,
I am sorry that you are experiencing issue with the Deriving Dates.
This was a bug that we already addressed June 17, 2014.
I also ran some tests in my test environment and everything seemed to be working fine. I created 2 Dates field in Workspace A, and in Workspace B I use a linking picklist as the pivot and able to derived both date fields in Workspace B
Please see the attachment below.
Please try to re-test it again. If you still experiencing issues. Please e-mail me at trung.nguyen@autodesk.com, and I can take a look at your tenant.
Thanks,
Trung