I'm trying to create a short Simulation/Animation of some Engineered Wall Panel Framing Being set, then Wall Shtg being applied, then Floor decking set on top of that. I can get the tasks top start at the tiimes' I want, but cannot get any of the durations to be less than 1-hour.....even though T/L can show down to 15-min intervals. What I'm trying to accomplish is new panels being set at a 30-min interval after the previous panel......but cannot drag the gannt to be less than 1 hr. Is there something I'm missing in regards to setting time(s).
Mike
Solved! Go to Solution.
Solved by lee.mullin. Go to Solution.
At the moment the Gannt chart only allows you to drag the start and end dates to the nearest hour. If you want more details on the times you can either bring these through from your scheduling software or you can manually edit them in the table view.
I hope this helps and I'll add an enhancement request to our system
Thanks Lee,
I'll try the editing as suggested.
Mike