I am using timeliner to create a amination.  Howerver ,  I foung if I change a task default starting date from N/A to a specified date , I can't change it back to N/A. 

 

Does anyone know how to set the task starting date or end date back to N/A for Timeliner?

 

Thanks

 

Jason

Employee
JeffH_ADSK
Posts: 149
Registered: ‎10-29-2009
Message 2 of 2 (104 Views)

Re: Timeliner task starting date issue?

11-12-2012 02:44 AM in reply to: li71we

This should be accomplished by editing the date and pressing the Del key.

 

Hope that helps,

 

Jeff



Senior Software Engineer
Navisworks
Autodesk Ltd.
Post to the Community

Have questions about Autodesk products? Ask the community.

New Post
Announcements
Have API Questions?
New Dedicated Forum for Navisworks API