Select items attached to a particular timeliner task

3 REPLIES 3
Reply
Message 1 of 4
Chris_Baze
390 Views, 3 Replies

Select items attached to a particular timeliner task

Is there a way to do this? You can select all the the items that are attached to tasks, but I have not found a way to select only the items attached to one particular task.

3 REPLIES 3
Message 2 of 4
jason.seck
in reply to: Chris_Baze

I don't have an answer, but here is an alternate workflow.  I create a selection set for all items assiciated with eaash task.  I then attach the selection set to the task.  I can then easily select any of those selection sets.

Jason Seck
BIM Coordinator
Black & Veatch, Water Division
Message 3 of 4
Chris_Baze
in reply to: Chris_Baze

Yeah, that's what I used to do until Navisworks started breaking up Revit files by level. Then I got lazy haha. I need to go back and update my search sets again.

Message 4 of 4
goyat.jean
in reply to: Chris_Baze

Maybe I don't understand the question, but can't you simply clik on the link showing what items were attached ("Attached" column) to the particular task in the Timeliner Task window?