Hello
I am running an actual project in Navis works 2014, the feedback from the field is that the task started
late and there is no possible finish date since work stop on site.
If I select actual in the timeliner simulation setting window and the tasks actual finish
date is set to N/A the simulation will not display the task.
Can this be change?
Best Regards Andre
I am also facing the same issue as koenigandr .
There are multiple tasks that have started and are 80-95% completed but dont have an Actual End Date in the Schedule.
I want to show such tasks in the Simulation Video as they are critical tasks.
Please help !!
Nope. Only two types of actuals interpreting by Navisworks. 0 and 100% . There is no way of showing the incomplete progress by updating just the percentage of work finished in actuals.
your suggestion should work..As every activity in a project will have some finish date ( actual finish or expected finish), based on which other activities will be driven. if not there is no meaning to a schedule. So you can either try with an Expected finish date or tentative project end date.
Hope my response is in line with your post. Correct me if I had taken it in some other way.