Good day,
I´m having a problem with the Inventor 2012 Task Scheduler.
I´ve done a couple of migration tasks over the last 2 months, actually quite some big tasks on our Vault Server.
Now I´m getting no more access to the application, it´s either showing a message that the server is busy and not responding or the application starts up and sits for a minute in the task bar and then opens up but still I can´t click any menus or create a report to control the tasks I´ve done earlier.
But I need to check the last couple of tasks to see which files have been succesfully migrated and which are not.
I know that I can view the logfiles manually but that still leaves me with no more tasks that I need to run to fix our database and Inventor files.
Let the application run with administrator rights doesn´t help either, I´m at a loss here. What else could be done to get
the task scheduler back up running?
All the best
Falk
The only solution for me was replacing the database for the Task Scheduler with the original one from the installation.
For anyone having the same problem, make a copy of the recent *.mdb´s and look for the fresh database on your installation disk.
It seems Task Scheduler is not capable of doing large migration datasets under WinXP 64, after 8 to 10 tasks in the database the application becomes completely unusable.
The question is, what other tool can be used for migrating a vault with 75.000 files?
I answered that question for myself with None.
You will have to live with another Autodesk 80% solution, which is the Task Scheduler.
Best wishes