Is there any way to track BOM changes. For instance you have an assembly that was checked in to the Vault. Later revision was made to it. Is there any way to keep track what parts were removed and what parts were added on the latest revision? Is there any tool to get such report?
Thank you,
Alex.
If you have vault pro it has an ECN system that can be taylored to do this I would imagine.
If this solved your issue please mark this posting "Accept as Solution".
Or if you like something that was said and it was helpful, Kudos are appreciated. Thanks!!!!
Not knowing exactly what you had, I figured I would throw it out there.
To the best of my knowledge, short of keeping very detailed revision notes in the revision block, iLogic may be your only other option for something like this.
If this solved your issue please mark this posting "Accept as Solution".
Or if you like something that was said and it was helpful, Kudos are appreciated. Thanks!!!!
No problem. Sorry I could not be of more help.
I have worked at places that did the same thing. But, we had an ECN # on the drawing and the ECN document
outlined everything that changed. Right down to the finest detail. That is why I suggested the ECN through vault pro.