Community
sometimes the beam to column and beam to beam get generated upside down?
We are required to have our bolting spaced at 70 from top of steel, then spaced at 70.
this seems to be a problem mainly with the shear plate connections.
Sometimes the connections are draw up side down so the 70 dim is fom bottom of steel?
the beams were inserted with the top centreline with zero rotation.