Create new project from existing issue

2 REPLIES 2
Reply
Message 1 of 3
Anonymous
333 Views, 2 Replies

Create new project from existing issue

Hello,

There are one issue in Plant3D that I think is necessary to resolve. When is created new project from existing ALL isometrics drawings is coping from existing project to new.

 Thanks

Regards

2 REPLIES 2
Message 2 of 3
Anonymous
in reply to: Anonymous

Yury,

 

Did you find the solution for your question? If so, please share the answer because I have the same problem. Thanks.

 

Regards

Message 3 of 3
Anonymous
in reply to: Anonymous

Usually what we used to do is to make a project configure the project with respect to specs and catalogue and also to isometrics required and save it.

You can now start your project by selct copy from template and continue on.

In your case it is simple... what you do, is rename and remove the folder of your isometrics to another location outside the project then make a new folder with the carrect name.

 

 

regards

 

Indesh