Which is best: multiple or single constructs for electrical systems?

506 Views, 4 Replies
08-23-2012 01:50 PM

I am wondering which of the following approaches is most effective and time-efficient in MEP 2013 (as applied to a single project):

 

  1.  Is it quicker and easier to have a separate construct for each type of system (lighting, power), showing that system's associated circuiting, switching, tags, et cetera, then creating views from those separate constructs?
  2. Or is it more effective to do all electrical work on a single construct, toggling between display configurations to isolate which system is being worked on at the time and to create separate views?

Currently I have separate constructs for lighting and power/systems, but was not able to provide a convincing argument as to why I should keep doing it that way.  Bear in mind that our company's construction drawings are almost entirely schematic in nature, without sections or elevations (thus far).

 

Any suggestions or pros/cons to either approach would be greatly appreciated!

 

Thank you!

 

Jon A. Hunt, LC

Hi, Joshua.

 

No noise yet.  I'm currently setting up a project using the single-construct approach for electrical, to compare with the multiple constructs I used on the previous project.  I will be happy to hear from other folks how they go about it, of course.

 

Thanks again.

Product Support
Joshua.Benoist
Posts: 518
Registered: ‎08-23-2006
Message 2 of 5 (479 Views)

Re: Which is best: multiple or single constructs for electrical systems?

08-27-2012 12:50 PM in reply to: jonh

Here in support, I've seen it both ways.  Some break them out because it helps with organization, especially on larger projects.  Some do lighting and power all in one, which makes circuiting and creation of panel schedules easier.

 

There are some great guys here in these forums with lots of electrical experience.  I invite them to weigh in here and share.

 

Thanks guys!

 

Joshua

 


______________________________________________________________

If my post answers your question, please click the "Accept as Solution" button. This helps everyone find answers more quickly!



Joshua Benoist, PE
Senior Support Specialist
Product Support
Autodesk, Inc.

Product Support
Joshua.Benoist
Posts: 518
Registered: ‎08-23-2006
Message 3 of 5 (466 Views)

Re: Which is best: multiple or single constructs for electrical systems?

08-29-2012 12:18 PM in reply to: Joshua.Benoist

Just following up and bumping this post back to the top.  Anyone want to weigh in here and share?

 

Joshua

 

 


______________________________________________________________

If my post answers your question, please click the "Accept as Solution" button. This helps everyone find answers more quickly!



Joshua Benoist, PE
Senior Support Specialist
Product Support
Autodesk, Inc.

Active Member
jonh
Posts: 9
Registered: ‎07-19-2012
Message 4 of 5 (464 Views)

Re: Which is best: multiple or single constructs for electrical systems?

08-29-2012 12:20 PM in reply to: Joshua.Benoist

Hi, Joshua.

 

No noise yet.  I'm currently setting up a project using the single-construct approach for electrical, to compare with the multiple constructs I used on the previous project.  I will be happy to hear from other folks how they go about it, of course.

 

Thanks again.

Jon A. Hunt, LC
*Expert Elite*
Keith.Brown
Posts: 1,237
Registered: ‎03-13-2008
Message 5 of 5 (445 Views)

Re: Which is best: multiple or single constructs for electrical systems?

08-30-2012 06:46 AM in reply to: jonh

If your computers can handle it then I think it is always best to get it all in the same drawing and organize everything using layer control, display control, etc.  This is especially true if you use the project management system.  Create different views for the different systems.  With everything in the same drawing it is easier to edit things as you move the project along.  Just be aware of the project size and how it could quickly grow out of control.  I always break my levels up into seperate drawings but try to keep each trade in one single drawing if I am able.


Keith Brown AutoCAD MEP BLOG | RSS Feed
AutoCAD MEP 2014 | Revit 2014 | EastCoast CAD/CAM V6.1 | Visual Studio 2013
────────────────────────────────────
⁞|⁞ Please use Mark Solutions!.Accept as Solution and Give Kudos!Give Kudos as appropriate. Thank you!
Post to the Community

Have questions about Autodesk products? Ask the community.

New Post
Need installation help?

Start with some of our most frequented solutions to get help installing your software.

New AutoCAD MEP Category!

The AutoCAD MEP forum has moved into it's very own category page, and can no longer be found within the Additional Product Forums.

Announcements
Do you have 60 seconds to spare? The Autodesk Community Team is revamping our site ranking system and we want your feedback! Please click here to launch the 5 question survey. As always your input is greatly appreciated.